| DAY | acres burned | Percent contained | Estimated Cost to Date | number of personnel |
| Sunday, July 21, 2002 | ||||
| Monday, July 22, 2002 | 15,000 | |||
| Tuesday, July 23, 2002 | 48,200 | |||
| Wednesday, July 24, 2002 | 55,000 | 5 % | ||
| Thursday, July 25, 2002 | 57,000 | 5 % | 53 crews, 10 helicopters, 117 engines, 203 overhead personnel, 17 bulldozers, 9 water tenders, 10 air tankers | |
| Friday, July 26, 2002 | 60,000 | 10 % | $5.2 Million | 58 crews, 13 helicopters, 102 engines, 203 overhead personnel, 17 bulldozers, 5 water tenders, 10 air tankers. Total Personnel: 1,560 |
| Saturday, July 27, 2002 | 62,000 | 30 % | $7.75 Million | 79 Crews, 14 Helicopters, 102 Engines, 263 Support personnel, 10 Dozers, 9 Water Tenders, 10 Air Tankers. Total Personnel: 1,655 |
| Sunday, July 28, 2002 | 66,000 | 30 % | $9.1 Million | 14 helicopters, 9 air tankers, 19 dozers, 23 water tenders, 125 fire engines, 54 handcrews, and 560 support personnel. Total personnel: 2,278. |
| Monday, July 29, 2002 | 73,000 | 30 % | $10.4 Million | 13 helicopters, 9 air tankers, 19 dozers, 23 water tenders, 125 fire engines, 51 handcrews, and 550 support personnel. Total personnel: 2,208 |
| Tuesday, July 30, 2002 | 80,000 | 35% | $11.5 Million | 13 helicopters, 9 air tankers, 14 dozers, 25 water tenders, 125 fire engines, 43 handcrews, and 291 support personnel. Total personnel: 1,755 |
| Wednesday, July 31, 2002 | 90,500 | 35% | $14.3 Million | 12 helicopters, 6 air tankers, 22 dozers, 33 water tenders,
100 fire engines, 62 handcrews, and 647 support personnel. Total personnel: 1,967. |
| Thursday, August 1, 2002 | 93,500 | 45% | $15.8 Million | 12 helicopters, 5 air tankers, 22 dozers, 30 water tenders,
80 fire engines, 46 handcrews, and 520 support personnel. Total personnel: 2,054. |
| Friday, August 2, 2002 | 98,000 | 50% | $19.4 Million | 13 helicopters, 3 air tankers, 15 dozers, 30 water tenders, 85 fire engines, 52 handcrews, and 552 support personnel. Total personnel: 1,870 |
| Saturday, August 3, 2002 | 100,000 | 50% | $19.4 Million | 13 helicopters, 3 air tankers, 13 dozers, 30 water tenders, 75 fire engines, 52 handcrews, and 552 support personnel. Total personnel: 1,870 |
| Sunday, August 4, 2002 | 100,800 | 50% | $20.6 Million | 12 helicopters, 3 air tankers, 13 dozers, 35 water tenders, 75 fire engines, 52 handcrews, and 584 support personnel. Total personnel: 2052 |
| Monday, August 5, 2002 | 101,200 | 55% | $20.6 Million | 12 helicopters, 3 air tankers, 13 dozers, 35 water tenders, 75 fire engines, 52 handcrews, and 584 support personnel. Total personnel: 2052 |
| Tuesday, August 6, 2002 | 105, 604 | 55 % | $22.3 Million | 12, helicopters, 3 air tankers, 11 dozers, 30 water tenders, 55 fire engines, 32 handcrews & 560 support personnel. Total personnel: 1,582 |
| Wednesday, August 7, 2002 | ||||
| Thursday, August 8, 2002 | 112,501 | 55% | $24.7 Million | 13 helicopters, 2 air tankers, 18 dozers, 37 water tenders, 75 fire engines, 28 handcrews, and 525 support personnel. Total personnel: 1,412 |
| Friday, August 9, 2002 | 116,214 | 60% | $24.7 Million | 13 helicopters, 5 air tankers, 9 dozers, 30 water tenders, 44 fire engines, 37 handcrews, and 219 support personnel. Total personnel: 1,412 |
| Saturday, August 10, 2002 | 117,447 | 70% | $26.7 Million | 12 helicopters, 6 air tankers, 9 dozers, 30 water tenders, 44 fire engines, 40 handcrews, and 223 support personnel. Total personnel: 1,342 |
| Sunday, August 11, 2002 | 121,225 | 70% | $28 Million | 12 helicopters, 8 air tankers, 8 dozers, 30 water tenders, 44 fire engines, 40 handcrews, and 224 support personnel. Total personnel: 1,392 |
| Monday, August 12, 2002 | 130,590 | 70% | $28.9 Million | 14 helicopters, 8 air tankers, 8 dozers, 31 water tenders, 46 fire engines, 44 handcrews, and 265 support personnel. Total personnel: 1,458 |
| Tuesday, August 13, 2002 | 130,876 | 70% | $30 Million | 12 helicopters, 6 air tankers, 8 dozers, 30 water tenders, 56 fire engines, 43 handcrews, and 259 support personnel. Total personnel: 1,465 |
| Wednesday, August 14, 2002 | 133,154 | 75% | $31.5 Million | 12 helicopters, 8 air tankers, 8 dozers, 24 water tenders, 60 fire engines, 38 handcrews, and 263 support personnel. Total personnel: 1,367 |
| Thursday, August 15, 2002 | 134,859 | 75% | $31.5 Million | 12 helicopters, 7 air tankers, 8 dozers, 24 water tenders, 61 fire engines, 45 handcrews, and 272 support personnel. Total personnel: 1,530 |
| Friday, August 16, 2002 | 136,280 | 85% | $33.9 Million | 12 helicopters, 8 air tankers, 8 dozers, 22 water tenders, 61 fire engines, 45 handcrews, and 254 support personnel. Total personnel: 1,541 |
| Saturday, August 17, 2002 | 139,550 | 87% | $25.3 Million | 12 helicopters, 8 air tankers, 7 dozers, 21 water tenders, 61 fire engines, 41 handcrews, and 283 support personnel. Total personnel: 1,477 |
| Sunday, August 18, 2002 | 142,815 | 87% | 12 helicopters, 7 air tankers, 8 dozers, 17 water tenders, 61 fire engines, 46 handcrews. Total personnel: 1,471 | |
| Monday, August 19, 2002 | 143,322 | 87% | 13 helicopters, 7 air tankers, 8 dozers, 17 water tenders, 69 fire engines, 46 handcrews. Total personnel: 1,494 | |
| Tuesday, August 20, 2002 | 147,227 | 87% | 15 helicopters, 8 dozers, 37 water tenders, 67 fire engines, 42 handcrews. Total personnel: 1,723 | |
| Wednesday, August 21, 2002 | 147,227 | 87% | 15 helicopters, 8 dozers, 37 water tenders, 67 fire engines, 4 handcrews. Total personnel: 1,712 | |
| Thursday, August 22, 2002 | 147,227 | 87% | 15 helicopters, 8 dozers, 39 water tenders, 67 fire engines, 40 handcrews. Total personnel: 1,712 | |
| Friday, August 23, 2002 | 149,482 | 87% | $40.7 Million | 17 helicopters, 8 dozers, 38 water tenders, 61 fire engines, 38 handcrews. Total personnel: 1,591 |
| Saturday, August 24, 2002 | 150,420 | 89% | $41 Million | 15 helicopters, 5 dozers, 41 water tenders, 61 fire engines, 35 handcrews. Total personnel: 1,580 |
| Sunday, August 25, 2002 | 150,420 | 89% | $41 Million | 17 helicopters, 3 dozers, 40 water tenders, 58 fire engines, 35 handcrews. Total personnel: 1,525 |
| Monday, August 26, 2002 | 150,420 | 91% | $43 Million | 16 helicopters, 2 dozers, 39 water tenders, 58 fire engines, 35 handcrews. Total personnel: 1,452 |
| Tuesday, August 27, 2002 | 150,696 | 94% | $44 Million | 16 helicopters, 2 dozers, 38 water tenders, 47 fire engines, 29 handcrews. Total personnel: 1,400 |
| Wednesday, August 28, 2002 | 150,696 | 97% | $44.7 Million | 16 helicopters, 1 dozers, 32 water tenders, 33 fire engines, 25 handcrews. Total personnel: 1,248 |
| Thursday, August 29, 2002 | 150, 696 | 100% | $45.7 Million | 15 helicopters, 1 dozers, 30 water tenders, 32 fire engines, 20 handcrews. Total personnel: 1,143 |